- The Mezzanine is up and erected.
- Stairs for the Mezzanine under construction
- Mezzanine Estimated Completion Time: Next 2 Weeks
- Plumbing related rough in work: 70% Complete
- Rough in work to be done by end of month
- Sinks, Faucets, Toilets installed by end of the year
- Electrical related rough in work: 70% Complete
- Pre-wiring for AV related work: 75% Complete
- Remaining work will start once ceiling is up and will take 2-4 weeks to complete
- Bathroom floors to be started first within the next 2 weeks
- Estimated completion in 4-6 weeks
- Selection for tiles and rugs for musallah, banquet hall, hallways, foyer, and rooms in progress
- Outside doors order placed 2 weeks ago
- To be available by end of October and installed within a week of arrival
- Work on curbs for heating and cooling units in progress
- Curbs are being installed on roof now and to be done within next 2 weeks
- After curb installation, heating and cooling units will be installed on roof by end of October
- Ceiling work will start in 3 weeks
- Estimated completion of all Phase A Ceiling work is end of the year
- The trim work (electrical switches, light fixtures, air return and supply, and ducts) will start in January
- Please don’t go inside new building as it’s an active site of construction and is dangerous
- OSHA fines are very heft if we are found not abiding by their laws
- Please make dua for the completion of Phase A and for us to make our move to our new home soon