Construction Updates

MEZZANINE

MEZZANINE

  • The Mezzanine is up and erected.
  • Stairs for the Mezzanine under construction
  • Mezzanine Estimated Completion Time: Next 2 Weeks

PLUMBING

  • Plumbing related rough in work: 70% Complete
  • Rough in work to be done by end of month
  • Sinks, Faucets, Toilets installed by end of the year
Plumbing
Electrical & AV

ELECTRICAL & AV

  • Electrical related rough in work: 70% Complete
  • Pre-wiring for AV related work: 75% Complete
  • Remaining work will start once ceiling is up and will take 2-4 weeks to complete

FLOORS

  • Bathroom floors to be started first within the next 2 weeks
  • Estimated completion in 4-6 weeks
  • Selection for tiles and rugs for musallah, banquet hall, hallways, foyer, and rooms in progress
Plumbing
Doors

DOORS

  • Outside doors order placed 2 weeks ago
  • To be available by end of October and installed within a week of arrival

MECHANICAL

  • Work on curbs for heating and cooling units in progress
  • Curbs are being installed on roof now and to be done within next 2 weeks
  • After curb installation, heating and cooling units will be installed on roof by end of October
Mechanical
Mechanical

MECHANICAL

  • Ceiling work will start in 3 weeks
  • Estimated completion of all Phase A Ceiling work is end of the year
  • The trim work (electrical switches, light fixtures, air return and supply, and ducts) will start in January

COMMUNITY REQUEST

  • Please don’t go inside new building as it’s an active site of construction and is dangerous
  • OSHA fines are very heft if we are found not abiding by their laws
  • Please make dua for the completion of Phase A and for us to make our move to our new home soon